left divider
left blue square  
left divider
left blue square  
left divider
left blue square  
left divider
left blue square  
left divider
left divider
left blue square  
left divider
left blue square  
left divider
left blue square  
left divider
left blue square  
left divider
left blue square  
left divider
left blue square  
left divider

scope

Task No. 1: Project Management

Task No. 2: Stakeholders and Operational Objectives

Task No. 3: Requirements Analysis

Task No. 4: High Level System Design

Task No. 5: Alternatives Analysis

Task No. 6: Recommendations

Task No. 7: Conceptual Design Reports

Task No. 8: Operations and Maintenance Plan

Task No. 9: Technical, Operational, and Institutional Issues

Task No. 10: City Concurrence

Task No. 11: Final Conceptual Design Report

Task No. 12: Strategic Implementation Plan

INTRODUCTION

This document defines the Scope of Work for the I-5/Telegraph Road Corridor Contract for Gateway Cities Traffic Signal Synchronization and Bus Speed Improvements Project (PROJECT). Work products described in this work statement will be completed and delivered by the CONSULTANT, Gardner Systems, to the County of Los Angeles Department of Public Works (DPW), in accordance with the terms of the Agreement. The entire PROJECT is intended to include, but not be limited to, system requirements development, system development and conceptual design, Plans, Specifications, and Estimates (PS&E) preparation, system implementation, system analysis, documentation, training, startup, maintenance, and project evaluation. This statement of work will apply to the Preliminary/Conceptual Design and the Project Management responsibilities associated with this task pertaining to Phase 1 of the PROJECT only. It is the County's intent to enter into supplemental agreement(s) with the CONSULTANT, and/or another contractor depending upon the outcome of the Preliminary/Conceptual Design Phase, for the remaining phases of this PROJECT. The following is an outline of the major phases of the PROJECT.

  • Phase 1: Conceptual Design Master Plan
  • Phase 2: Detailed Design
  • Phase 3: System Implementation
  • Phase 4: Construction Inspection Assistance
  • Phase 5: System Acceptance Testing
  • Phase 6: Documentation and As-Built Plans
  • Phase 7: Staff Training
  • Phase 8: Before and After Study System Evaluation
  • Phase 9: Start-up and On-Going System Maintenance

The list below describes the five major system improvement components of this PROJECT. Pursuant to this Agreement, the CONSULTANT shall complete Phase 1 for each of these components.

1. Advanced Traffic Management System (ATMS)

This component consists of the development, design, selection, and implementation of a complete interjurisdictional ATMS. The ATMS will include the hardware and software necessary to allow monitoring, controlling, and coordinating the operation of traffic signals and, in the future, other Intelligent Transportation Systems (ITS) field devices along Telegraph Road. The system will be operated from individual agency work stations which will have traffic surveillance capabilities through detecting and monitoring signal status, traffic congestion and incidents, and will display this information through a fully integrated mapping function. The system will also be able to detect equipment malfunctions which will enable the operator to initiate appropriate maintenance operation responses and various other responses to traffic events and congestion either manually or automatically using an expert system application.

It is anticipated that the system will provide once-per-second monitoring of traffic signals, interjurisdictional communication with localized control, and levels of security to restrict access to unauthorized users. The system will also employ strategies such as interjurisdictional data sharing, cooperative efforts in timing plan development, a coordinated response to arterial incidents, congestion and special events, and traffic data analysis. Additionally, the system will provide local and regional level access, controls, and connections to the future I?105 Corridor Traffic Management Center (TMC), and other future regional traffic forum TMCs, the City of Los Angeles' ATSAC System, Los Angeles County TMC, and Caltrans Districts 7 and 12 TMCs.

As part of this component, each municipality will be provided with work stations capable of controlling its jurisdiction's traffic signals, as well as the ability to monitor all signals along the I-5/Telegraph Road Corridor from its remote work station site. Also, provisions shall be made to allow an individual city to control other jurisdiction's signals full time or during nonpeak hours and weekends. These control strategies will be accomplished by the execution of multijurisdictional agreements. Typically, a work station will consist of a computer system located at each jurisdiction's city hall or other location and will be fully capable of satisfying that jurisdiction's traffic management needs, as well as the requirements of the PROJECT. This component will provide the hardware and software necessary to provide these capabilities to each I-5/Telegraph Road Corridor Agency.

For all jurisdictions in the Corridor with existing traffic control systems, an analysis will be completed to determine the need for replacement or modification of their respective systems. In the event that the PROJECT recommends, and the city desires to maintain its system, then the ATMS will provide an interface and any required equipment to enable communication and insure compatibility with the other jurisdictions in the Corridor. In this instance, the ATMS will be a hybrid system which will consist of a combination of new and existing systems.

Another element of the ATMS is the establishment of a comprehensive Vehicle Detection System for the Corridor to supplement the existing traffic signal detectors and to collect real-time traffic data and information at key intersection locations where monitoring of traffic is critical to the movement of vehicles. The amount, type, and location of system detectors will be determined by the CONSULTANT after careful consideration of the user needs, system functional requirements, and available budget.

Although an Advanced Traveler Information System (ATIS), Closed Circuit Television (CCTV) cameras, Changeable Message Signs (CMS), and other ITS elements are not part of this PROJECT, the ATMS must be capable of accommodating the installation of these elements in the future, and be able to provide the necessary control, map display, and monitoring functionality.

The development of this ATMS will require a traffic management system operations plan which will identify the existing and the desired level of operation, and recommend the most suitable ATMS to fit those needs. The CONSULTANT will be required to select and implement a Commercial Off-the-Shelf (COTS), or other previously developed, advanced traffic management system software capable of interfacing with the Countywide Architecture currently under design by Los Angeles County.

As part of the overall Gateway Cities Forum Project, DPW is working on Traffic Signal Synchronization Program (TSSP) improvements on Telegraph Road. The work includes intersection and signal controller upgrades, signal timing, and a proposed installation of a new signal at the I-5 northbound off-ramp on Telegraph Road. Since the implementation of the ATMS being developed in this PROJECT will also involve signal controller upgrades, the CONSULTANT will be required to coordinate with DPW staff on controller upgrade requirements.

2. Local City Control Site

This component will include a schematic floor plan, facility specification, staffing, training and operations and maintenance requirements of a typical local city control site. Additionally, the CONSULTANT will identify a preliminary site for each city's control site proposed to be installed by the PROJECT by conducting an on-site inspection and make recommendations on necessary alterations to this work space to provide the needed functionality. In future phases, it is anticipated the CONSULTANT will install the control sites for the affected agencies.

3. System Integration

This component will integrate all of the PROJECT'S components to ensure an open system architecture is maintained and all PROJECT components are integrated in a seamless environment with a common interface. The ATMS must have the ability to interface with all related ITS elements implemented through other projects such as other regional traffic forum projects, other city systems, Caltrans systems, and all Southern California ITS Priority Corridor Steering Committee projects, such as the Showcase Project. The local city control sites must also be integrated with future subregional TMC(s) in the Gateway Cities Forum, Los Angeles County, and Caltrans Districts 7 and 12. The system must also be integrated and compatible with the Countywide Architecture currently under development by DPW's consultant under the San Gabriel Valley Signal Operation and Maintenance (SOM) Pilot Project. The CONSULTANT shall also consider future integration with other potential stakeholders and users mentioned above.

The CONSULTANT shall also develop user interface requirements in order to interface to and coordinate with the above projects. The CONSULTANT shall generate top-level data flow diagrams for each Graphic User Interface (GUI) and review the interface prototype with the users. A standardized and user-friendly interface will also be developed by the CONSULTANT as part of this component to facilitate system expansion, operation, maintenance, and training. The CONSULTANT will provide all developer tools and detailed instructions to enable agency staff to modify the user interfaces to reflect future expansion and changes in the system, e.g., addition of signals, cameras, desired changes to database layouts, etc., after PROJECT completion.

4. Communication System

This component includes the design of a communication system capable of supporting the recommended inter-jurisdictional ATMS design. The installation of a communications network is essential to support the traffic signal operation, monitoring, and control capabilities of the ATMS, as well as information exchange with other jurisdictions, stakeholders, and systems. These may include the State of California Department of Transportation (Caltrans) Freeway Management System, Los Angeles County arterial traffic control system, and other existing and planned systems outside the Gateway Cities area. In designing the system, the CONSULTANT must research and take advantage of opportunities to reuse existing or planned communications facilities.

This communication network must include links between the field infrastructure units (such as the system detectors and controllers) and each jurisdiction's traffic control site. Additionally, it must include communication links between each local city site and any regional or sub-regional control site, such as the Gateway Cities I-105 Corridor TMC and the County of Los Angeles TMC.

Since the communication system will drive the capability of all system components, both present and future ITS elements must be considered in the design. Additional primary considerations must be the expandability to include other potential stakeholders and users, system expansion to include additional signals, and the cost effectiveness of the system. Possible communications medium technology may include, but not be limited to, twisted pair cable, leased telephone lines, fiber optic cables, spread spectrum radio, very small aperture terminals, or a combination of the above.

Any recommendations made by the CONSULTANT for this PROJECT shall be for the implementation of "open systems" and shall be made after careful review of potentially suitable systems for use in the Gateway Cities Forum. This includes completed systems or systems currently under development in other traffic forums. The recommendations made shall occur in close coordination with the Intermodal and Jurisdictional Integrated Network Environment (IMAJINE) Project, any applicable Southern California Priority Corridor ITS Steering Committee Projects, Los Angeles/Ventura County ITS Coordinating Committee Projects, and Regional Traffic Forum Projects, throughout Los Angeles County to ensure a seamless environment with a common interface. The CONSULTANT shall build on previous work undertaken by these projects and committees and, where applicable, use completed work products to avoid unnecessary work or duplication of effort in this PROJECT.

The CONSULTANT shall perform the tasks and subtasks for Phase 1 pertaining to the five major traffic signal system improvement components of the PROJECT and provide deliverables as described herein.

For each deliverable outlined in this Agreement, the CONSULTANT shall submit to the COUNTY draft versions for review and comment. If the first draft is acceptable to the COUNTY, COUNTY will distribute copies to all affected agencies for review and comment prior to being returned to CONSULTANT for preparation of final documents. If the first draft submitted to COUNTY is not acceptable to the COUNTY, it will be returned to CONSULTANT until it is in a form acceptable for distribution to the affected cities.

The CONSULTANT is required to address all agency comments. Any agency comment which will not be incorporated into a report shall be discussed, either verbally or in writing, with the COUNTY and the writer of the comment.

A draft deliverable shall be considered accepted by COUNTY and CONSULTANT may invoice COUNTY for the cost of the deliverable when COUNTY determines, in its sole discretion, that the draft deliverable is acceptable for distribution to the affected cities. A final deliverable shall be deemed accepted by the COUNTY and CONSULTANT may invoice the COUNTY for the cost of the deliverable upon receipt by CONSULTANT of a written notification of acceptance from the COUNTY.

The CONSULTANT shall use the standard DPW software set forth below when preparing deliverables. The CONSULTANT shall provide deliverables in bound hard copies and in a file format (on diskette[s]) or via E-Mail) importable to the standard DPW software. Current DPW standard software is as follows.

  • WordPerfect or Microsoft Word - Word Processing
  • LOTUS 1-2-3 or Microsoft Excel - Spreadsheet
  • Microsoft Project - Project Management and Project Plan

Exhibit B (Schedule of Deliverables and Payment Schedule) of this Agreement provides the payment schedule for each deliverable included in this Statement of Work. Payment shall be made in accordance with the Agreement.

PHASE 1: CONCEPTUAL DESIGN MASTER PLAN

The CONSULTANT shall prepare the Conceptual Design Report and plans for each PROJECT component. This will be accomplished by first preparing a detailed and comprehensive user and system functional requirements document. Based on this document, the CONSULTANT shall perform an alternatives analysis to select the best alternative to satisfy the identified user and functional needs. These recommendations will culminate in a Conceptual Design Master Plan document for each PROJECT component which will identify improvement locations, the type of technology to be used, the conceptual design and specifications, a detailed description of the tasks involved with the implementation and installation of each PROJECT component, and cost estimate. This information will serve as the foundation for the Detailed Design Phase (Phase No. 2) and will be used as a starting point for building consensus on a variety of institutional issues including cost sharing and possible funding sources for operating and maintaining the proposed improvements once they are in place.

The CONSULTANT shall complete the draft or final version (if a draft version is not to be completed for a specific task) of all deliverables for the tasks in this phase within __ months of receipt of the Notice to Proceed for this PROJECT from the Director.

ATMS

In this task, the CONSULTANT will obtain the user needs and system functional requirements of the ATMS. Based on this information, the CONSULTANT will evaluate various alternative systems and recommend the most suitable for the PROJECT. In addition, the CONSULTANT will research the existing Vehicle Detection System , propose upgrades and new installations as necessary to enable the selected ATMS to function as efficiently and effectively as possible. In addition, it is the intention that the system has the capability to respond to and interface with future functionality which provides for inter-agency coordination of operations (e.g in response to incidents and special events)

Local City Control Site

The CONSULTANT shall provide the Conceptual Design documents for the physical accommodations which will be necessary for the design and implementation of the local city control sites. CONSULTANT shall also identify any additional hardware and software necessary for local control site operations not included in other tasks. Primarily, this shall involve the Conceptual Design of the following.

� The equipment, furnishings, and staff necessary to operate a typical local city control site; and
� Any other component, such as additional hardware and software required to bring the local control sites to full operation.

This task will include the Conceptual Design of a typical local city control site. This Conceptual Design will include a schematic floor plan, and control site facility specifications identifying required building and system operational, functional, staffing, training, and O&M requirements. Additionally, the CONSULTANT will be responsible for identifying preliminary locations for each local city control site by conducting on site inspections. The CONSULTANT shall also identify those proposed agency control site locations requiring physical alterations to meet the typical control site design characteristics.

Communications

In the initial stage of the PROJECT, the CONSULTANT will conduct an analysis of the user needs and functional requirements of the communications system. Based on this analysis, the CONSULTANT will evaluate several alternative communication modes and recommend the most suitable for the I-5/Telegraph Road Corridor.

System Integration

The CONSULTANT shall prepare a Conceptual Design for integrating the I-5/ Telegraph Road transportation system components in a seamless environment with a common interface by ensuring that an open system architecture is maintained. Since the work to be performed under this task deals primarily with the operational issues resident in the integration process of the I?5/Telegraph Road Corridor, technical systems integration conceptual design shall be performed by the CONSULTANT in conjunction with the Conceptual Design of the four transportation system components of this PROJECT.

Another primary component of this task is the integration with other existing systems within the Gateway Cities area such as those under development under Project IMAJINE and the I-105 Project. Integration with other systems throughout Los Angeles County is also anticipated. These systems include, but should not be limited to, the City of Los Angeles' Automated Traffic Control System, the Southern California Priority Corridor Showcase Project, and other systems currently under development in other forum areas. This task will define the system interface and integration requirements for these systems. The Conceptual Design of a standardized and user friendly interface will also be completed by the CONSULTANT as part of this task to facilitate system maintenance and training.